Whitehead Street Road Work

Crews are in the final phases of finishing up the complete makeover of lower Whitehead Street.

Starting Wednesday April 27th, crews will be milling the street. They will work one block at a time starting at Fleming Street and working toward Front Street. This will mean they will be closing each block one block at a time while they work. The closed blocks will be made accessible to emergency vehicles only.

Depending on weather, the milling is scheduled to be completed by the weekend, at which time the road will be open to all traffic.

On Monday, May 1st, crews will begin the installation of the new asphalt surface. This work will also close a block at a time as the roadbed is rebuilt. Some intersections may remain closed overnight during this process, but detours will be clearly marked.

By Wednesday, May 4th, paving will begin, which will complete the Whitehead Street project.